Reconstruction Of Glass Furnaces

A method for lifting the metal structures of a glass furnace bath to a height of 0.7-1.4m without dismantling the structures used in the plant for cold repair is described. The total mass of the lifted metal structures is 200 tons.l The time of cold repair is reduced by around ten days.