[Czech Republic] Vetropack Invests In Horn Equipment

Czech glass container manufacturer Vetropack Moravia has invested in the reconstruction of its 52 furnace at its Kyjov plant. The project included both the drainage of the old furnace and the demolition and gutting of its entire surface. This was followed by the complete reconstruction of the furnace, using 4000 tons of refractory and 600 tons of steel. Vetropack commissioned Horn Glass Industries of Germany to supply the complete gas heating equipment for the furnace and the forehearth, as well as the regenerators, three HVR 500 batch chargers, glass level control equipment and additional boosting equipment for the throat, the barrier and the furnace. The project was completed in 97 days, including foundations and construction work.

Author
Un-named
Origin
Unknown
Journal Title
Glass Int May 2011 12
Sector
Container glass
Class
C 4422

Request article (free for British Glass members)

[Czech Republic] Vetropack Invests In Horn Equipment
Glass Int May 2011 12
C 4422
Are you a member?
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.
1 + 14 =
Solve this simple math problem and enter the result. E.g. for 1+3, enter 4.